We received your letter dated 2026-05-09 regarding the heater package and your position that it falls outside SC-13-11-00 §3.7. We agree the clause language is brief; the governing instrument here is CO 150 r2 §A.4, executed 2026-04-22, which expressly adds the heater package (3× 1.5 MBH units) to Calder Pools scope at $84,000.
Please confirm receipt of that line item before the May pay-app cycle (cut-off 2026-05-22). If you wish to contest the CO retroactively, the path is a written notice under CCDC 17 §10.2 within 14 days.
Available for a call this week if helpful.
— Arjun Mitchell, Project Manager · Meridian Construction